How an Interior Project Actually Runs

The six stages of a Twin Space Studio project in Pune, what happens in each, what we need from you, and what you receive at the end of every stage.

Every studio publishes a process diagram. This is ours written out properly: what happens at each stage, what we need from you, what you get, and where projects usually go wrong.

Stage 1 — Discover

What happens: We meet, at the flat where possible. We measure, photograph and check the things that decide what is feasible — floor-to-slab height in more than one place, where the plumbing runs, the distribution board, which walls are structural, and how material will physically get into the building.

What we need from you: How you actually live. Who cooks and how often, who works from home and when, what you own that needs storing, and what annoyed you about the last home.

What you get: An honest first read on feasibility and budget range, before any drawing exists.

Stage 2 — Conceptualise

What happens: We develop the plan — zoning, circulation, where storage goes and what each room is for. This is the stage that decides whether the home works. Material and colour follow it rather than leading it.

What we need from you: Decisions on room use, particularly the third bedroom in a 3 BHK. Reference images are useful but the plan matters more.

What you get: Layouts, a design direction and indicative visuals.

Stage 3 — Design and plan

What happens: Detailed drawings. Elevations for every joinery run, the electrical layout, the ceiling and lighting plan, and the plumbing changes. Every unit is drawn to actual dimensions taken on site.

What we need from you: Sign-off on the electrical layout. This is the single most schedule-critical approval in the project, because everything behind the wall depends on it.

What you get: A complete drawing set and the itemised quote. The figure on that quote is the figure at handover.

Stage 4 — Select and finalise

What happens: Materials, finishes, hardware and stone are selected and confirmed. Long-lead items are identified and ordered first. Society paperwork, registration and lift bookings are started.

What we need from you: Timely selection, particularly of stone. Late stone selection is the most common cause of a delayed Pune project, because it blocks the kitchen and every counter behind it.

What you get: A confirmed specification and a dated programme.

Stage 5 — Execute

What happens: Site work, in sequence: demolition and civil changes, electrical and plumbing, ceilings, carpentry, painting, then installation. Our carpenters build in your flat rather than shipping in flat-pack, so every unit is fitted to the actual wall.

What we need from you: Availability for decisions. Most site questions need an answer within hours, not days.

What you get: A single point of contact, both founders on the project, and progress you can see.

Stage 6 — Deliver and stylise

What happens: Snagging, correction, deep cleaning, then styling — soft furnishing, art placement, the final lighting settings.

What you get: A finished home and a snag list that has already been worked through rather than handed to you.

Where projects actually go wrong

Three things cause almost every delay, and none of them is design.

Late client decisions, particularly stone and the electrical layout, both of which block work behind them.

Society access that was not confirmed in writing before the schedule was built.

Starting the conversation after possession rather than before, which routinely costs four to five weeks for no design reason.

Related

See how long each stage takes, how payments are staged and what it costs.

To start a project, call Pooja Dhoot on +91 82080 93011 or Dimple Marathe on +91 88881 77217.

Questions

Common questions

What are the stages of an interior project?

Six: Discover, Conceptualise, Design and plan, Select and finalise, Execute, and Deliver and stylise. Each has a defined output, and the itemised quote is issued at the end of stage three.

What is the most schedule-critical decision I have to make?

Sign-off on the electrical layout, followed by stone selection. Everything behind the wall depends on the first, and the kitchen and every counter depend on the second.

Do I get a quote before detailed drawings?

You get an honest budget range at stage one, before any drawing exists. The itemised quote comes with the complete drawing set at the end of stage three, and that figure is the figure at handover.

Who will I actually be dealing with?

Both founders, from first sketch to snag list. You are not handed to a project manager you have never met once the drawings are signed.

What causes projects to run late?

Late client decisions on stone and the electrical layout, society access that was not confirmed in writing, and starting the conversation after possession rather than before. Design changes are rarely the cause.