Living in the Flat During a Renovation

How we phase a Pune renovation so a family can stay in the home — dust control, which room goes last, and what it adds to the programme.

About half our renovation clients stay in the flat through the work, usually because three months of rent costs more than the saving, and sometimes because moving out of a home held for thirty years is not a simple proposition. It is entirely workable. It changes the sequence, and it adds about two weeks.

How we phase it

The principle is that one bedroom and one bathroom stay usable at all times, and the kitchen goes last.

We start with the rooms you can most easily do without — typically the second bedroom and the living room — and complete them fully before opening the next. That means dust and disruption move through the flat rather than filling it, and you always have somewhere finished to retreat to.

The kitchen is deliberately last. A family can live without a spare bedroom for a fortnight but not without somewhere to cook, so we set up a temporary arrangement — usually an induction plate, a sink connection and a table in a finished room — before the existing kitchen comes out.

Dust control

This is what actually determines whether living in is tolerable, and it is where most contractors are casual.

We seal the working zone with a floor-to-ceiling barrier, not a hung sheet. Doorways get zipped access panels. Air-conditioning and any ducted route between zones is sealed off, because dust travels through it. Grinding and cutting happen outside the flat wherever possible, and where it cannot, with extraction at the tool.

Floors in the finished zones stay protected throughout, and the site is cleaned at the end of every working day rather than at the end of the week.

Grouping the wet work

The single most disruptive thing in a renovation is the water going off. Left unplanned it goes off repeatedly — once for the kitchen, once per bathroom, once for the utility.

We group all plumbing changes into a single block so the supply is interrupted once rather than five or six times, and we tell you the dates in advance so you can plan around them.

Noise

Demolition, chasing and core drilling are the loud phases, and they are front-loaded — usually the first ten to fourteen working days. If anyone in the house works from home or sleeps during the day, that is the window to be elsewhere if you can.

Societies frequently restrict noisy work to a narrower window than general working hours, commonly 10am to 5pm. See society rules for interior work.

What it adds

Roughly two weeks on a ten-to-twelve week programme. The time goes into sequencing that would otherwise happen in parallel, setting up and moving dust barriers, and the temporary kitchen arrangement.

We state this at quoting stage rather than discovering it in week eight. A contractor who quotes the same duration whether you stay or move out has not thought about the sequence.

What we ask of you

Pack and move what you can before we start — the fewer possessions in the working zone, the faster and cleaner the work. Anything fragile or valuable should be out of the flat entirely rather than covered.

Agree the noisy-work window with us so we can front-load it around your calendar, and be reachable for decisions during working hours. Most site questions need an answer within the hour.

When we recommend moving out

Honestly, there are cases. A full strip-out of a small flat where there is no room that can be completed and sealed first. A household with a newborn, or someone with a respiratory condition. And any project where the entire plumbing layout is changing, which makes a single wet-work block impossible.

We say so when it applies rather than taking the work on terms that will make everyone miserable.

Related

See renovating an older flat, how long a project takes and interior designers in Kothrud, where most of this work happens.

To talk through a renovation, call Pooja Dhoot on +91 82080 93011 or Dimple Marathe on +91 88881 77217.

Questions

Common questions

Can we stay in the flat during a renovation?

Usually yes, and about half our renovation clients do. We phase it room by room so one bedroom and one bathroom stay usable throughout, and the kitchen goes last after a temporary arrangement is set up.

How much longer does it take if we stay?

About two weeks on a ten-to-twelve week programme. The time goes into sequencing that would otherwise run in parallel, moving dust barriers, and setting up the temporary kitchen.

How do you control dust?

A sealed floor-to-ceiling barrier rather than a hung sheet, zipped access panels at doorways, air-conditioning and duct routes sealed off, cutting done outside the flat where possible with extraction at the tool, and a clean at the end of every working day.

How often will the water be off?

Once, if it is planned properly. We group all plumbing changes into a single block rather than interrupting the supply separately for the kitchen, each bathroom and the utility, and we give you the dates in advance.

When would you advise moving out instead?

A full strip-out of a small flat with no room that can be completed and sealed first, a household with a newborn or someone with a respiratory condition, or a project where the entire plumbing layout changes so a single wet-work block is impossible.